MANAJEMEN PROYEK KONSTRUKSI PEMBANGUNAN REVETMENT DI TELUK MANADO KOMPLEK PASAR BERSEHATI
Keywords:
Project Management, Construction, Revetment Earned Value ManagementAbstract
This research aims to 1 find out the estimated time by implementing EVM Earned Value Management during the implementation time so that it is in accordance with the initial plan for the revetment construction project in Manado Bay and 2 Find out the additional costs of the project when experiencing delays and acceleration This research is located at the construction of a revetment in the Bersehati market complex Manado city Data analysis uses the Earned Value Concept method The research results show that in the 19th week the ETC calculation reached IDR 50 896 353 625 36 from the initial budget of IDR 11 120 996 728 with a deviation in the increase in budget value of IDR 5 562 722 563 35 The estimated time for project completion in the 19th week was 86 8 days indicating that completion was delayed by around 167 days from the original plan which should have been only 20 days < p>